Reeded Glass Shower Screen - London

This London walk-in shower screen showcases the perfect mix of modern design and classic British style. The black grid frame with reeded glass panels creates a striking look while giving just the right amount of privacy for daily use.

Front view of black-framed reeded glass shower screen with middle bars in London

Three-Sided Shower Design

The three-sided design forms a sturdy shower enclosure without a door. The top bar connects all sides to create a solid structure that stands firm with no wobble or shake, even with its full 2200mm height.

This walk-in shower screen uses reeded glass that lets light through while keeping shapes blurred. The textured glass adds depth to the bathroom and works well with the bold black frame and chocolate wall tiles.

Three-sided black framed shower screen with reeded glass in London bathroom

Black Grid Frame

The black grid design gives this shower screen its striking look. Each panel has middle bars that split the glass into smaller sections, adding visual interest and extra strength to the tall structure.

Our bespoke shower frames use carbon fibre inside the aluminium to make them as rigid as steel. This gives the frame its solid feel without making it too bulky or heavy.

Corner view of walk-in shower enclosure with black grid frame and reeded glass

Seamless Installation

The shower screen sits on a white 1200mm x 1200mm tray with no visible fixtures inside or outside. The clean lines and hidden fixings create a smooth look that flows with the rest of the bathroom design.

The doorless entry makes this shower glass panel easy to use and gives the bathroom a more open feel. The terrazzo-style floor adds a fun touch that works well with the industrial frame style.

Product Specification

Style

Walk-in Shower Screen

Metal Finish

Black

Glass Type

8mm reeded glass

Frame Style

Framed with Grid

Special Features

Three Sides, Middle Bars

Price Range

£££

Product Dimensions

Width

1200mm

Depth

1200mm

Height

2200mm

Custom sizes available - contact us for bespoke measurements

When Will Your Reeded Glass Shower Screen Be Ready?

Walk-in designs prioritize seamless integration with your bathroom layout. The Reeded Glass Shower Screen timeline varies based on wall preparation and structural requirements.

📋 Multiple Items: Each additional shower enclosure may extend Design, Assembly, and Installation by approximately 1 working day. However, orders of 5+ units benefit from streamlined production processes that reduce per-unit time. We'll provide an optimized timeline for your specific project.

Tiling Ready

Faster Option

Your walls are tiled and ready for fluted glass installation. We'll take precise measurements and begin the specialized textured glass production process.

Site Survey 1 day
Precise measurements and photos
Design & 3D 3 days
Create and approve your custom design
Parallel Production 20 days
Frame (20d) and Glass (8d) made simultaneously
Assembly 3 days
Glass fitted into frames
Installation 2 days
Professional on-site installation

✓ Efficient Process: With tiling complete, we take all measurements in one visit and run frame and glass production simultaneously.

17
Working Days Total
13
Production Days
2
Days On-Site

Timeline Considerations for This Project

  • This uses our standard black finish so the frame production time is fast. We keep black coating in stock which saves time compared to bespoke finishes.
  • The reeded glass requires special processing and lamination which takes longer than regular glass. The lamination process adds extra time but creates a safer and more durable product.

Tiling Not Ready

Extended Timeline

Your walls need tiling before fluted glass installation. We'll take rough measurements for design visualization, prepare for specialized glass production, then finalize measurements after tiling.

Initial Visit 1 day
Rough measurements and photos
Design & 3D 3 days
Create initial design based on rough measurements
Frame Production 20 days
Can start while tiling is in progress
Waiting for Tiling Variable
Depends on your tiling schedule
Final Measurements 1 day
Precise measurements once tiling is complete
Design Adjustments 1 day
Update design if dimensions changed
Glass Production 8 days
Cut to exact measurements
Assembly 3 days
Glass fitted into frames
Installation 2 days
Professional on-site installation

💡 Flexible Timeline: The waiting period begins after frame production (day 6) and varies based on your tiling schedule. If your tiling is completed during our frame production period, we can arrange the final measurements earlier and advance the entire schedule - moving final measurements, design adjustments, glass production, assembly, and installation to start as early as day 5 (right after design confirmation). The total timeline shows the minimum 21 working days if tiling is ready when frames are done.

21
Working Days Minimum
15
Production Days
2
Days On-Site

Interested in a Similar Design?

Let our experts create a bespoke shower solution perfectly tailored to your space. From survey to installation, we handle everything with precision and care.

Contact Us

Understanding Our Pricing

Each symbol reflects a full-service estimate, including survey, design, production, and installation. We only offer complete packages — no supply-only options.

Prices are adjusted based on real projects and assume the installation is within one hour's travel from one of our offices. Travel beyond this range may increase the price.

VAT is not included and will be added where required. Displayed prices are for guidance only and reflect localised, complete installations.

Price Range Guide

  • £ Up to £1,500
  • ££ £1,501 - £2,500
  • £££ £2,501 - £3,200
  • ££££ £3,201 - £8,000
  • £££££ £8,001+